The Ecclesbourne School Phase 2

 

The Ecclesbourne School Phase 2

The project involved the construction of a new kitchen extension and refurbishment and conversion of existing Kitchen, Refectory, Drama, Music and Science buildings with the majority of the works being carried out whilst the school was occupied. This required detailed phasing and handovers to ensure that the schools daily operations were not affected including working adjacent to and during crucial exam periods.

The kitchen refurbishment included both relocating the existing kitchen installation and supplementing this with new equipment where necessary including the construction of a new “walk in” cold room and individual “fresh” and “dry” produce stores.

The laboratory works included forming new laboratories with specialist gas and service installations along with new fume cupboards.

The music block refurbishment including creating 6 new sound proof practice rooms as well as the refurbishment of existing teaching space.